Beowulf: Update re Kallak Iron Ore Project June 2012

Se nyheten från Beowulf

Beowulf (AIM: BEM; Aktietorget: BEO), the AIM and Aktietorget traded mineral exploration company which owns several exploration projects in Sweden, is pleased to announce encouraging preliminary results from initial drilling, since 29 May 2012, conducted at Kallak North with a second drill rig now in operation. The ongoing initial phase of the Company's 2012 drill programme is currently intended to comprise up to approximately 7,000m of drilling aimed primarily at defining the limits of the extension of the Kallak North deposit, both in terms of breadth and depth.

In addition, Beowulf announces the outstanding assay results in respect of its 2011 drill programmes conducted on both Kallak South and Kallak North.

2012 drill programme
The "Big Bertha" drill rig initially drilled an extension to the pre-existing drill hole KAL 10 019 at a 45 degree inclination. Strong iron (Fe) mineralisation was encountered at a depth of 79.5m, which continued down to 313.8m, from where weaker mineralisation was noted until reaching the total target length of 374.5m.
A second hole (an extension to the pre-existing drill hole KAL 10 001 drilled at a 60 degree angle on the east-west drill section previously defined as 7414 200 N (RAK coordinate system)) has also been completed to test the extension at depth of the Kallak North deposit. This second drill hole encountered continuous mineralisation from 85m to 454m, with strong mineralisation down to a depth of 410m. This corresponds to approximately 350m vertical depth from ground surface of outcropping iron mineralisation, thereby confirming the presence of a substantial depth and width of iron mineralisation at the 7414 200 N drill section on the Kallak North deposit.
The rig is currently drilling an extension to a third hole (labeled KAL 10 026B) at an angle of 45 degrees with a total target length of 350m.
Drill cores from the first two holes were scanned in the field at the drill site by a highly sensitive hand held magnetic susceptibility meter, with automatic average registrations over the core lengths, and are being transported to the ALS laboratory at Öjebyn, Sweden, for logging and analytical preparation.
A second drill rig, "Agnetha", is now also in operation and has commenced drilling at a 45 degree angle to test the North/East boundary of the Kallak project area, as well as seeking to define the depth of the Kallak North deposit.
Assay results from the initial holes in the ongoing programme are expected in August 2012.
2011 assay results
The outstanding assay results received in respect of the 32 hole drilling campaign completed on Kallak South in 2011 are set out in the table below:
See tables in attached document!

Dr Jan Ola Larsson (Fil. Kand, PhD, DIC), has reviewed and approved the technical information contained within this announcement in his capacity as a qualified person, as required under the AIM rules. Dr Larsson is Technical Director of the Company and has over 30 years relevant experience within the natural resources sector.

Clive Sinclair-Poulton, Executive Chairman of Beowulf, commented: "The 2011 results indicate the presence of substantial deposits of iron mineralization at both Kallak North and South.
We are delighted with the encouraging preliminary results from the initial holes in the first phase of our ongoing 2012 drill programme at Kallak North, which have shown strong indications of iron ore to considerable depths and far deeper than previously encountered. We look forward to making swifter progress utilising the second drill rig and to reporting assay results in due course.

The drilling campaign has been designed to establish the boundaries of Kallak North and we continue to believe that the wholly owned Kallak project represents a most attractive and exciting asset within our diverse portfolio."

Notes to Editors:

The chemical laboratory ALS Scandinavia AB will complete all sample preparation and analysis of the cores from the 2012 Kallak drilling programme, having been similarly involved in Beowulf's previous drilling on the deposits in 2010 and 2011.
Kallak North currently has an independent JORC Code compliant Inferred Resource estimate of 131.6Mt grading at 28% iron (Fe) completed by GeoVista AB. Considerably more in-fill drilling is required in order to increase the existing estimated tonnage and JORC classification.


London, 2012-06-21
Enquiries:

Beowulf Mining Plc
Clive Sinclair-Poulton, Chairman Tel: +353 (0)85 739 2674

Strand Hanson Limited
Matthew Chandler / Simon Raggett Tel: +44 (0)207 409 3494

Alexander David Securities Limited
David Scott Tel: +44 (0)207 448 9820

Lothbury Financial Services Limited
Gary Middleton / Michael Padley Tel: +44 (0)207 868 2010


or visit http://www.beowulfmining.net



Se nyheten från Beowulf  Läs mer om Beowulf

Publicerat: 6/21/2012 11:30:03 AM


  • Danderydsgatan 10
  • 114 86 Stockholm
  • Telefon: 08 - 545 038 00
  • Fax: 08 - 611 35 62
  • info(snabel-a)aktietorget(punkt)se